“How much do you want upfront?” is the question that separates established builders from cash-flow casualties, and homeowners lose more money to deposits than to almost any other single mistake. The rules of thumb are simple, and worth holding to even when a builder you like pushes back.
What’s normal, by type of work
| Work | Typical deposit | Why |
|---|---|---|
| General building (extension, loft, renovation) | 0–10% | Labour-led; materials bought as needed |
| Kitchen supply & fit | 25–50% of supply | Units are made/ordered to your spec |
| Windows & doors | 25–50% | Manufactured to measure |
| Bathrooms | 10–25% | Sanitaryware ordered upfront |
| Small trades (electrician, plasterer, decorator) | £0 | Paid on completion or weekly |
| Bespoke joinery / stone | 30–50% | Genuine made-to-order |
The pattern: deposits are legitimate where they fund something ordered specifically for you, and suspicious where they fund the builder’s general cash flow. A £60,000 extension needs no meaningful deposit; a £15,000 German kitchen genuinely does.
The Federation of Master Builders gives around 10% as a common guide for a deposit on larger projects, particularly where materials or made-to-order items have to be bought in advance.1
When to refuse
Decline, or renegotiate, when:
- the deposit exceeds ~25% on general building work;
- it’s demanded in cash;
- the reason given is “to secure your slot” months ahead (a small booking fee of £100–£500 is one thing; thousands is another);
- the builder is a recently incorporated company with no trading history, check Companies House;
- there’s pressure to pay before a written contract exists.
An established firm asking for a big deposit is usually telling you its last job hasn’t paid or its credit accounts are exhausted. Either way, you’d be lending money to a business the trade suppliers won’t.
Protecting whatever you do pay
- Pay by credit card if you can, even £100 of it. Under Section 75 of the Consumer Credit Act, paying any part of a contract priced at more than £100 and up to £30,000 by credit card makes the card company jointly liable for the builder’s breaches, including a deposit that vanishes with a dissolved company.2 It’s the strongest free protection in consumer law.
- Tie the deposit to named orders. “Deposit applied to the window order with [supplier], receipt to be provided” turns a cash-flow gift into a traceable purchase.
- Use deposit protection where offered. TrustMark expects its registered businesses to have financial protection covering prepayments such as deposits, and some trade bodies offer deposit and guarantee insurance; genuine schemes issue you a policy document, not a logo on a letterhead.3
- Never pay a deposit for labour. Labour is paid in arrears, against work done, through stage payments released only once each stage is complete.1
- Get it in the contract: amount, what it covers, and that it’s deducted from the first stage payment.
Deposits and your cancellation rights
If you signed at home (as many building contracts are), the Consumer Contracts Regulations give you a 14-day cooling-off period from the day the contract is made.4 A deposit must be refunded within 14 days if you cancel within that period, less a proportionate charge only where you expressly asked for work to start early.5 Builders who never give you the cancellation information extend that window by up to 12 months, a point covered in our contracts pillar.6 The regulations do not apply to contracts for the construction of new buildings, so a new-build or self-build contract is outside them.7
If the deposit has already gone wrong
Paid, and the builder has gone quiet or under? Move in this order: written demand with a deadline; Section 75 claim if any part went on credit card; chargeback (via your bank, for debit cards, typically within 120 days); then the formal dispute route.8 Speed matters, card schemes run time limits, and insolvent builders’ creditor queues reward the early.
The best protection, though, is the boring one: vet the builder, keep the deposit small, and keep every pound you pay slightly behind the value standing on site.
This guide is general information for homeowners in England and Wales, not legal advice.
References (8)
Figures in this note were checked against the sources below on 30 September 2026. Superscript numbers in the text point to them. Every source the site cites, by topic.
- 1technicalgoodFederation of Master Builders, guidance.RN-8ZTC0XThe Federation of Master Builders' homeowner guide to choosing and paying a builder. It says a small deposit is common on larger projects where materials or made-to-order items are bought in advance, with around 10% as a guide.
- 2technicalvery strongThe National Archives (legislation.gov.uk), legislation.RN-JFS7HZSection 75(1) gives the debtor under a debtor-creditor-supplier agreement within section 12(b) or (c) a like claim against the creditor for any misrepresentation or breach of contract by the supplier, making creditor and supplier jointly and severally liable. Section 75(2) entitles the creditor to be indemnified by the supplier. Section 75(3) sets the limits: the section does not apply to a non-commercial agreement, nor so far as the claim relates to any single item with a cash price not exceeding 100 pounds or more than 30,000 pounds, nor to certain short-period running-account credit agreements. Section 75(4) preserves the claim even where the debtor exceeded the credit limit or breached a term of the agreement, and section 75(5) lets the creditor join the supplier to the proceedings. This is the basis for claiming a builder's default from a credit card issuer where any part of the payment was made on the card.
- 3technicalstrongTrustMark, guidance.RN-W9CM4RTrustMark's page on the financial protection its registered businesses must offer. It lists prepayments such as deposits among the things the protection must cover, and advises checking the provider's cover before contracting.
- 4technicalvery strongThe National Archives (legislation.gov.uk), guidance.RN-LG5W1ERegulation 30 sets the 14-day cancellation period for distance sales of goods, running from delivery; regulation 28 excludes goods made to the consumer's specifications.
- 5technicalvery strongThe National Archives, guidance.RN-4KYUTJRegulation 36 of the Consumer Contracts Regulations 2013 governs services started in the cancellation period: an express request, on a durable medium for off-premises contracts, and a proportionate payment on cancellation.
- 6technicalvery strongThe National Archives, guidance.RN-J1Y65ZRegulation 31 of the Consumer Contracts Regulations 2013, which extends the cancellation period by up to 12 months where the trader fails to give the required cancellation information.
- 7technicalvery strongThe National Archives, guidance.RN-820095Regulation 6 of the Consumer Contracts Regulations 2013 lists contracts outside the Regulations, including those for the construction of new buildings or substantially new buildings by conversion.
- 8technicalsupplier figureVisa, guidance.RN-YKGMIDVisa's UK consumer page on chargebacks, written by the card scheme that sets the rule. It states the 120-day window for a chargeback claim on a Visa debit or credit card.
-
How to choose a trusted builder in the UK, Federation of Master Builders, accessed 30 September 2026. fmb.org.uk
-
Consumer Credit Act 1974, section 75, legislation.gov.uk, accessed 30 September 2026. legislation.gov.uk
-
Providing Financial Protection for Homeowners, TrustMark, accessed 30 September 2026. trustmark.org.uk
-
The Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013, regulation 30, legislation.gov.uk, accessed 30 September 2026. legislation.gov.uk
-
The Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013, regulation 36, legislation.gov.uk, accessed 30 September 2026. legislation.gov.uk
-
The Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013, regulation 31, legislation.gov.uk, accessed 30 September 2026. legislation.gov.uk
-
The Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013, regulation 6, legislation.gov.uk, accessed 30 September 2026. legislation.gov.uk
-
Chargeback: Debit & Credit Card Purchase Disputes, Visa, accessed 30 September 2026. visa.co.uk