Get the payment schedule right and almost nothing else can go catastrophically wrong: if the builder folds, walks, or falls out with you, the damage is capped at days of work rather than months of money. Get it wrong, paying ahead of the work, and every other protection in the contract is fighting uphill.

The golden rule

The value of completed work on site should always slightly exceed the total you’ve paid. Not the other way round, not even for a week. This single discipline means that at any moment the deal could end and you could pay someone else to finish with the money still in your account. Builders call clients like this “safe”; insolvency practitioners call the others “creditors”.

A worked example: £80,000 rear extension

StageMilestone%Cumulative
1Foundations poured and inspected10%10%
2Masonry to DPC, oversite complete10%20%
3Walls to wallplate15%35%
4Roof on, structure watertight15%50%
5First fix (electrics, plumbing, joinery)12%62%
6Plastering complete10%72%
7Second fix complete12%84%
8Decoration, floors, commissioning11%95%
9Practical completion + snagging5% retention100%

Adjust the shape to the job, keep the principles: no deposit-shaped stage 0 (see deposits), each stage tied to something you can stand in front of and see finished, and a meaningful final slice held for snagging.1

Milestones, never dates

A schedule that pays “£8,000 on the 1st of each month” pays for time passing, not work done, the programme slips and the money doesn’t. Milestone triggers self-correct: slow job, slow money. This is also fairer to a fast builder, who gets paid sooner by finishing sooner.

Define each milestone unambiguously.1 “Roof complete” invites argument; “roof structure, covering, flashings and rainwater goods complete” doesn’t. The JCT Building Contract for a Home Owner/Occupier allows the price to be paid in agreed interim payments, so write the stages into it; on a builder’s own paperwork, attach the table.2

Valuing a stage before you pay

For most stages a 15-minute walk-round together is enough: is the milestone genuinely complete, including the fiddly ten percent? Photograph the state of work at each payment, it’s your evidence trail if anything later goes to dispute. On projects over ~£150k, or where the schedule is monthly valuations rather than milestones, paying a quantity surveyor a few hundred pounds per visit to certify valuations is money well spent, see when a QS is worth it.

Pay promptly once a stage is genuinely done, within 7 days, ideally faster. The moral authority to insist on quality comes partly from being the client who always pays on the nail.

When the builder pushes for more, sooner

Requests to bring money forward, “can you do stage 4 now, we’ve nearly finished stage 3”, are how sound schedules erode. A one-off with a reason (a big materials order landing) can be accommodated by paying for the materials on delivery, against invoice, not by advancing a labour stage.1 A pattern of pushing is your earliest, clearest signal of a business in cash trouble: tighten, don’t loosen. The contracts pillar covers the deposit and retention rules that pair with this guide.

This guide is general information for homeowners in England and Wales, not legal advice.

References (2)

Figures in this note were checked against the sources below on 30 September 2026. Superscript numbers in the text point to them. Every source the site cites, by topic.

  1. 1technicalfairCitizens Advice, guidance.RN-IED4GGCitizens Advice sets out six steps for a homeowner before work starts: check if you need permission or approval, find good traders, get quotes before deciding, check that you and your trader have insurance, get a written contract, and know what to do if there are problems. Advice applies to England, with separate versions for Northern Ireland, Scotland and Wales. It names the professional registers to search: a planning consultant on the Royal Town Planning Institute website, a surveyor on the RICS website and an architect on the Architects Registration Board website. Warns that without the permission or approval needed you might be fined, prosecuted, made to put things right or undo the work, and may have problems selling later. Confirms planning permission is usually needed to build something new such as an annexe, to make a major change such as an extension, or to change the use of a building.
  2. 2technicalstrongThe Joint Contracts Tribunal, guidance.RN-267X3CJCT's product page for its homeowner building contract. It says the contract is for a homeowner dealing directly with the contractor and suits small domestic work such as extensions.
  1. Before you get work done on your home, Citizens Advice, accessed 30 September 2026. citizensadvice.org.uk

  2. Building Contract for a Home Owner/Occupier, JCT, accessed 30 September 2026. jctltd.co.uk