Trades & Labour
170 sources in the library on trades & labour. Each one says what the document covers and what it is good for. Name a source to see which document it is and where to read it. One at a time. Page 3 of 5.
- very strong RN-BXZ3F2
The National Archives (legislation.gov.uk)
Section 51 of the Consumer Rights Act 2015 governs the case where no price was ever fixed. It applies where (a) the consumer has not paid a price or other consideration, (b) the contract does not expressly fix a price or say how it is to be fixed, and (c) nothing treated as included under section 50 fixes one either. Where all three apply, subsection (2) treats the contract as including a term that the consumer must pay a reasonable price and no more, and subsection (3) makes what is reasonable a question of fact. This is the provision a homeowner relies on when a trade started work on a handshake and later issued an inflated invoice: the invoice is not automatically the price.
- very strong RN-WUJM74
The National Archives (legislation.gov.uk)
Section 52(1) applies where the contract does not expressly fix the time for the service to be performed or say how it is to be fixed, and where no information treated as included under section 50 fixes the time either. In that case section 52(2) treats the contract as including a term that the trader must perform the service within a reasonable time, and section 52(3) makes what is reasonable a question of fact. Section 52(4) points to section 54; the remedy for breach of the reasonable time term is a price reduction under section 56, not repeat performance. This is the provision to cite when a builder has no contractual completion date and has overrun.
- very strong RN-QWQLI0
The National Archives (legislation.gov.uk)
Section 53 sets the boundary of Chapter 4 of the Consumer Rights Act 2015 (services). Subsection (1) provides that nothing in the Chapter affects any enactment or rule of law imposing a stricter duty on the trader, so sector rules such as Gas Safety (Installation and Use) Regulations 1998 duties or the Building Regulations sit on top of the section 49 reasonable care and skill term rather than being displaced by it. Subsection (2) makes the Chapter subject to any other enactment that defines or restricts the rights, duties or liabilities arising in connection with a service. Useful when a homeowner is told the Consumer Rights Act is the only standard the trade has to meet.
- very strong RN-ZQCZ3Z
The National Archives (legislation.gov.uk)
Section 54(3) gives the consumer two statutory remedies where the service does not conform to the contract: the right to require repeat performance under section 55 and the right to a price reduction under section 56. Section 54(4) gives a price reduction where the trader breaches a section 50 term that does not relate to the service itself, and section 54(5) gives a price reduction for breach of the section 52 reasonable time requirement. Crucially section 54(6) preserves other remedies instead of or in addition to these, provided the consumer does not recover twice for the same loss, and section 54(7) lists them: claiming damages, recovering money paid where the consideration has failed, specific performance, specific implement, relying on the breach against the trader's own claim under the contract, and treating the contract as at an end. Section 54(1) confirms these rights do not displace consistent contractual rights.
- very strong RN-AJNJD0
The National Archives (legislation.gov.uk)
Section 57 is the anti-exclusion clause for service contracts. Subsection (1): a term is not binding on the consumer to the extent it would exclude the trader's liability under section 49 (reasonable care and skill). Subsection (2): the same for section 50 (information given about the trader or service being binding), subject to section 50(2). Subsection (3): a term restricting liability under sections 49 to 52 is not binding if it would stop the consumer recovering the price paid. Subsection (4) extends this to terms that exclude or restrict a right or remedy, make it subject to a restrictive or onerous condition, disadvantage a consumer for pursuing it, or exclude rules of evidence or procedure. Subsection (5) covers preventing a duty arising at all; subsection (6) preserves arbitration agreements; subsection (7) points to Schedule 3 for enforcement.
- very strong RN-8QHXF5
The National Archives (legislation.gov.uk)
Section 62(1) and 62(2) make an unfair term of a consumer contract and an unfair consumer notice not binding on the consumer, while 62(3) still lets the consumer rely on the term if they choose. Section 62(4) sets the test: a term is unfair if, contrary to the requirement of good faith, it causes a significant imbalance in the parties' rights and obligations under the contract to the detriment of the consumer. Section 62(5) requires fairness to be judged by the nature of the subject matter and by all the circumstances existing when the term was agreed, together with all the other terms of that contract or any contract it depends on; 62(6) and 62(7) apply the same test to notices. Section 62(8) preserves the separate exclusion-of-liability rules in sections 31, 47, 57 and 65. This is the provision for challenging a non-refundable deposit clause or a one-sided variation clause in a builder's terms.
- very strong RN-TD41J9
The National Archives (legislation.gov.uk)
Section 1(1) imposes a duty on anyone taking on work for or in connection with the provision of a dwelling, whether by erection, conversion or enlargement, owed both to the person to whose order the dwelling is provided and to every person who later acquires a legal or equitable interest in it, to see that the work is done in a workmanlike or professional manner, with proper materials, and so that the dwelling will be fit for habitation when completed. Section 1(2) treats a person working to another's instructions as discharging the duty to the extent the work follows them properly, except where they owed and failed in a duty to warn of defects in the instructions; section 1(3) says merely agreeing to a specified manner, materials or design is not giving instructions. Section 1(4) brings a business that arranges for another to do the work within the duty. Section 1(5) fixes the accrual of the cause of action at the date the dwelling was completed for Limitation Act 1980 purposes, with a fresh accrual for any later rectification work when that further work is finished. The duty runs to subsequent owners, which contract claims do not.
- very strong RN-KQZJYU
The National Archives (legislation.gov.uk)
Schedule 20 to the DMCC Act 2024 lists 32 practices that are unfair in all circumstances, needing no proof that the average consumer was affected. All 32 came into force on 6 April 2025. The ones that bite in home improvement are at the top of the list: falsely claiming to be a signatory to a code of conduct; falsely claiming a code has been endorsed by a public or other body; displaying a trust mark, quality mark or equivalent without the required authorisation; and falsely claiming that a trader, its practices or a product has been approved, endorsed or authorised. Also directly relevant are bait advertising and bait-and-switch, false claims of limited availability to force a decision, presenting statutory consumer rights as a special feature of the offer, fake or incentivised reviews, creating the impression the consumer cannot leave the premises, ignoring a request to leave or not to return to the consumer's home except to enforce a contract, persistent unwanted solicitation, and supplying unrequested products then demanding payment or return.
- very strong RN-CW4UOI
The National Archives (legislation.gov.uk)
Section 226 of the DMCC Act 2024 replaced the misleading actions provision of the Consumer Protection from Unfair Trading Regulations 2008 and came into force on 6 April 2025, so it is the current law when a trade misdescribes itself or the work. A commercial practice is a misleading action if it involves (a) the provision of false or misleading information relating to a product, a trader or any other matter relevant to a transactional decision; (b) an overall presentation likely to deceive the average consumer even where each individual statement is accurate (subsection (3)); (c) marketing that creates confusion with a competitor's product or distinguishing mark; or (d) failure to comply with a mandatory requirement of a code of conduct the trader has claimed to follow, limited by subsection (5) to requirements allowing the trader no discretion and capable of verification. Subsection (2) confirms that information which is literally true but presented in a misleading way counts. This is the provision behind claims about being 'registered', 'approved' or 'insured' when they are not.
- very strong RN-43Q4DG
The National Archives (legislation.gov.uk)
The definitive list of what counts as a statutory nuisance in England and Wales, which is the legal hook for most neighbour and building-work complaints. Section 79(1) names, among others: (a) any premises in such a state as to be prejudicial to health or a nuisance, which is the route used against damp and disrepair; (b) smoke emitted from premises; (c) fumes or gases emitted from premises; (d) dust, steam, smell or other effluvia arising on industrial, trade or business premises; (e) any accumulation or deposit; (fb) artificial light emitted from premises, which covers security lighting; (g) noise emitted from premises; and (ga) noise from a vehicle, machinery or equipment in a street. Each limb requires the matter to be prejudicial to health or a nuisance. Section 79(1) also places a duty on every local authority to inspect its area for statutory nuisances and, where a person living in its area complains, to take such steps as are reasonably practicable to investigate. Section 79(1A) excludes matters caused by land being in a contaminated state, and section 79(2) excludes Crown defence premises from the smoke, artificial light and noise limbs.
- very strong RN-9WXESB
The National Archives (legislation.gov.uk)
The private route that lets an individual go to the magistrates' court directly, without waiting for the council, when aggrieved by a statutory nuisance; in Scotland the equivalent is a summary application to the sheriff. If satisfied the nuisance exists, or that though abated it is likely to recur, the court must make an order requiring the defendant to abate it within a specified time and to execute any works necessary, or prohibiting recurrence, and may also impose a fine not exceeding level 5 on the standard scale. Section 82(3) allows the court, where the nuisance makes premises unfit for human habitation, to prohibit their use for habitation until they are made fit. Section 82(4) fixes who is sued: normally the person responsible, but (b) where the nuisance arises from any defect of a structural character it is the owner of the premises, and (c) where the person responsible cannot be found, the owner or occupier. Section 82(5) makes each of several responsible persons liable even where their own contribution would not by itself be a nuisance.
- very strong RN-M1UGU8
The National Archives (legislation.gov.uk)
Section 104 of the Construction Act defines what a construction contract is, which decides whether the Act's payment and adjudication regime applies at all. Subsection (1): a construction contract is an agreement with a person for the carrying out of construction operations, for arranging for construction operations to be carried out by others whether under sub-contract or otherwise, or for providing that person's own labour or the labour of others for construction operations. Subsection (2) extends the definition to agreements to do architectural, design or surveying work, or to provide advice on building, engineering, interior or exterior decoration or the laying out of landscape, in relation to construction operations. Contracts of employment and agreements about matters unconnected with construction operations are excluded. Read this with section 105 for the list of construction operations and section 106 for the residential occupier exclusion that removes most homeowner contracts from the regime.
- very strong RN-ZE4N9A
The National Archives (legislation.gov.uk)
Section 107 of the Housing Grants, Construction and Regeneration Act 1996 originally restricted the Act's adjudication and payment provisions to agreements in writing. It was repealed in full by the Local Democracy, Economic Development and Construction Act 2009, taking effect on 1 October 2011 in England and Wales and 1 November 2011 in Scotland. The practical consequence is that a construction contract no longer has to be in writing for the statutory right to adjudicate to apply, so an oral or partly oral agreement can still be adjudicated. For homeowners the caveat remains section 106, which excludes a contract with a residential occupier from the Act, so this matters most where a homeowner is dealing with a contractor's own subcontractor chain or where the parties have adopted the Scheme by contract.
- very strong RN-LOJL3V
The National Archives (legislation.gov.uk)
The statutory adjudication timetable, which is fast by design and is why builders and subcontractors use it against each other, though section 106 excludes contracts with a residential occupier so a homeowner cannot rely on it unless their contract adopts it voluntarily. A party may give notice at any time of an intention to refer a dispute, dispute including any difference. The contract must provide a timetable aimed at appointing the adjudicator and referring the dispute within 7 days of that notice, require the adjudicator to reach a decision within 28 days of referral or a longer agreed period, and allow the adjudicator to extend the 28 days by up to 14 days with the consent of the referring party. The adjudicator must act impartially and may take the initiative in ascertaining the facts and the law, and may correct a clerical or typographical error in the decision. The decision is binding until the dispute is finally determined by legal proceedings, arbitration or agreement, and the parties may agree to treat it as final. The adjudicator and their employees and agents are not liable except for acts or omissions in bad faith. Where a contract fails to comply with subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply instead.
- very strong RN-NT0BCV
The National Archives (legislation.gov.uk)
Section 14B of the Limitation Act 1980 is the absolute cut-off for negligence claims against a builder, designer or engineer where no personal injury is involved. Subsection (1): an action for damages for negligence, other than one to which section 11 or 11ZA applies, shall not be brought after the expiration of fifteen years from the date, or if more than one from the last of the dates, on which there occurred any act or omission alleged to constitute negligence and to which the damage is alleged to be attributable. The fifteen years runs from the negligent act itself, not from the date the homeowner discovered the problem, and it overrides the more generous three-year date-of-knowledge extension in section 14A. In practice a latent defect discovered sixteen years after the work was done is out of time in negligence however reasonable the delay in noticing it.
- very strong RN-AUJII4
The National Archives (legislation.gov.uk)
Section 8 of the Limitation Act 1980 explains why a building contract executed as a deed is worth insisting on. Subsection (1): an action upon a specialty shall not be brought after the expiration of twelve years from the date on which the cause of action accrued. Subsection (2) confirms this does not override any shorter period prescribed elsewhere in the Act. A specialty is a contract executed as a deed, so where a homeowner and contractor sign the building contract as a deed the claim window for breach is twelve years from breach rather than the six years that section 5 gives for a simple contract. That difference matters for defects that take years to surface, such as inadequate foundations, failed damp proofing or a roof that only leaks under sustained driving rain. Read alongside section 14B, which imposes a fifteen year longstop on negligence claims, and the Defective Premises Act 1972 periods extended by the Building Safety Act 2022.
- very strong RN-HZOFM6
The National Archives (legislation.gov.uk)
Regulation 13 of CDM 2015 is the duty set that lands on the main builder once the client's duties transfer under regulation 7, and it is the answer to who is responsible when three trades are tripping over each other. Paragraph (1): the principal contractor must plan, manage and monitor the construction phase and coordinate health and safety matters so that, so far as is reasonably practicable, the work is carried out without risks to health or safety. Paragraph (2): in deciding design and technical aspects and in estimating how long tasks will take, the general principles of prevention must be taken into account, which is the hook against programme-driven corner cutting. Paragraph (3): the principal contractor must organise cooperation between contractors, coordinate implementation of the legal requirements and ensure employers and the self-employed apply the principles of prevention consistently. Paragraph (4): it must ensure a suitable site induction is given, that reasonable steps prevent unauthorised access, and that welfare facilities complying with Schedule 2 are provided throughout the construction phase. Paragraph (5) requires liaison with the principal designer.
- very strong RN-CDUYB1
The National Archives (legislation.gov.uk)
Regulation 15 of CDM 2015 is the duty list a homeowner can hold a builder to on an ordinary domestic job. Paragraph (2): the contractor must plan, manage and monitor the construction work so that, so far as is reasonably practicable, it is carried out without risks to health or safety. Paragraph (7): the contractor must not employ or appoint a person unless that person has, or is in the process of obtaining, the necessary skills, knowledge, training and experience for the task. Paragraphs (8) and (9): workers must be given appropriate supervision, instructions and information, including the identity of persons with health and safety responsibilities, emergency procedures and risk assessment findings, plus a suitable site induction where the principal contractor has not already given one. Paragraph (10): reasonable steps must be taken to prevent access by unauthorised persons, which is the basis for demanding a properly secured site next to a public footpath or where children are present.
- very strong RN-7AQOAI
The National Archives (legislation.gov.uk)
Regulation 4 of the CDM Regulations 2015 is the client duty set that transfers to the contractor or principal contractor for a domestic client under regulation 7. Paragraph (1): the client must make suitable arrangements for managing the project, including the allocation of sufficient time and other resources. Paragraph (2): those arrangements must ensure the work can be carried out safely and that welfare facilities are provided. Paragraph (3): the arrangements must be maintained and reviewed throughout the project. Paragraph (4): pre-construction information must be provided promptly to every designer and contractor. Paragraph (5): a construction phase plan must be drawn up before the construction phase begins and the principal designer must prepare and maintain the health and safety file. Paragraph (6): the client must take reasonable steps to ensure the principal designer and principal contractor comply. Paragraph (7): on disposing of an interest in the structure the client must pass the health and safety file to the new owner and explain its purpose, which is why the file should be handed over at completion of an extension.
- very strong RN-RM3MX4
The National Archives (legislation.gov.uk)
Regulation 5 of CDM 2015 sets the trigger that catches almost every renovation using separate trades. Paragraph (1): where there is, or it is reasonably foreseeable that there will be, more than one contractor working on a project, the client must appoint in writing a designer with control over the pre-construction phase as principal designer, and a contractor as principal contractor. Paragraph (2): the appointments must be made as soon as is practicable and in any event before the construction phase begins. If the client fails to appoint, the client is treated as taking on those duties under regulations 11 to 14. Read with regulation 7, a homeowner who directly engages a builder plus a separate electrician and plumber has more than one contractor, so the appointments must exist even though the duties default to the contractor in control of the work.
- very strong RN-X9NPAR
The National Archives (legislation.gov.uk)
Regulation 9 of CDM 2015 sets what an architect, architectural technologist or engineer must do before drawing anything, and the first duty is the one most homeowners never see performed. Paragraph (1): a designer must not commence work in relation to a project unless satisfied that the client is aware of the duties owed by the client under the Regulations, so a designer who never mentioned CDM to a domestic client is already in breach. Paragraph (2): in preparing or modifying a design the designer must take into account the general principles of prevention and any pre-construction information to eliminate, so far as is reasonably practicable, foreseeable risks to anyone carrying out or liable to be affected by construction work, maintaining or cleaning the structure, or using it as a workplace. Paragraph (3): where risks cannot be eliminated they must be reduced or controlled through the design, with information given to the principal designer and included in the health and safety file. Paragraph (4): the designer must take all reasonable steps to provide sufficient information with the design to help the client, other designers and contractors comply with their own duties.
- very strong RN-7PYVSZ
The National Archives (legislation.gov.uk)
Regulation 19 of SI 2013/3134 makes failure to give cancellation information a criminal offence, not merely a civil breach. Paragraph (1): a trader is guilty of an offence if it enters into an off-premises contract to which regulation 10 applies but fails to give the consumer the information listed in paragraph (l), (m) or (n) of Schedule 2 in accordance with that regulation, that is the right to cancel, the model cancellation form, and the liability for return costs. Paragraph (2): on summary conviction the trader is liable to a fine not exceeding level 5 on the standard scale, which in England and Wales has been unlimited since 12 March 2015. This is the hook for a Trading Standards report where a home improvement salesperson signed a contract in the kitchen and never mentioned cancellation.
- very strong RN-XD6UCF
The National Archives (legislation.gov.uk)
Regulation 29(1) gives the consumer the right to cancel a distance or off-premises contract at any time within the cancellation period, without giving any reason and without incurring any liability, subject to four named exceptions: regulation 34(3) on enhanced delivery the consumer chose, regulation 34(9) on diminished value where the consumer handled the goods beyond what is necessary to establish their nature, characteristics and functioning, regulation 35(5) on the cost of returning goods, and regulation 36(4) on service supply the consumer asked to begin early. Regulation 29(2) starts the cancellation period when the contract is entered into and ends it in accordance with regulation 30 or 31, which set the 14 day periods for goods and services. Regulation 29(3) also lets a consumer withdraw an offer before a contract is formed, again with no reason and no liability. This is the hinge provision for cancelling an online or doorstep materials order.
- very strong RN-CQVQWF
The National Archives (legislation.gov.uk)
Regulation 31 of SI 2013/3134 is the penalty a trade pays for not handing over cancellation information. Paragraph (1) applies it where the trader did not give the consumer the information on the right to cancel required by paragraph (l) of Schedule 2. Paragraph (2): if the trader supplies that information within 12 months beginning with the first day of the 14 days in regulation 30(2) to (6), the cancellation period instead ends 14 days after the consumer receives it. Paragraph (3): otherwise the cancellation period ends 12 months after the day it would have ended under regulation 30. In plain terms a homeowner who was never given a cancellation notice can have up to 12 months and 14 days to cancel, not 14 days.
- very strong RN-S8FA8S
The National Archives (legislation.gov.uk)
What the trader must pay back and by when after a distance or off-premises contract is cancelled. Regulation 34(1) requires the trader to reimburse all payments received from the consumer other than payments for delivery. Regulation 34(3) then requires the outbound delivery charge to be reimbursed too, but only up to the amount the consumer would have paid for the least expensive common and generally acceptable kind of delivery the trader offered, so a customer who paid for next-day or timed delivery gets only the standard rate back. Regulation 34(5) sets the deadline on a sales contract at 14 days after the trader receives the goods back or, if earlier, 14 days after the consumer supplies evidence of having sent them back. Regulation 34(6) sets 14 days from being informed of the decision to withdraw for other contracts. Regulation 34(9) is the trader's protection: where the value of the goods is diminished by handling beyond what is necessary to establish their nature, characteristics and functioning, the trader may recover that amount from the consumer up to the contract price.
- very strong RN-0WGBH6
The National Archives (legislation.gov.uk)
Regulation 38 of SI 2013/3134 deals with everything bolted onto a cancelled home improvement contract. Where a consumer withdraws an offer or cancels under regulation 29(1), any ancillary contract is automatically terminated without cost to the consumer, subject to the exceptions in paragraph (1)(a) to (d). The trader must tell any other trader with whom the consumer has an ancillary contract that the cancellation has happened. An ancillary contract is defined as one under which the consumer acquires goods or services related to the main contract, supplied either by the trader or by a third party under an arrangement with the trader. This is the provision that pulls a finance agreement, an extended warranty or a bolt-on insurance-backed guarantee down with the cancelled building contract.
- very strong RN-63UGBD
The National Archives (legislation.gov.uk)
Regulation 5 of the Control of Asbestos Regulations 2012 is the provision that obliges a contractor to establish whether asbestos is present before starting. An employer must not undertake work in demolition, maintenance or any other work which exposes or is liable to expose its employees to asbestos in any premises unless either (a) it has carried out a suitable and sufficient assessment as to whether asbestos, what type, in what material and in what condition, is present or liable to be present; or (b) where there is doubt, it assumes asbestos is present and that it is not chrysotile alone, and observes the applicable provisions of the Regulations. In practice this is why a refurbishment and demolition survey is commissioned before a soffit, artex ceiling, garage roof or old floor tile is disturbed in a property built or refurbished before the 1999 ban, and why a contractor who simply rips it out is in breach.
- very strong RN-5HLATC
The National Archives (legislation.gov.uk)
Regulation 8 of the Control of Asbestos Regulations 2012 is the provision that separates a licensed asbestos contractor from a general builder. Paragraph (1): an employer must hold a licence granted under paragraph (2) before undertaking any licensable work with asbestos. Paragraph (2): HSE may grant a licence where it considers it appropriate and the applicant has applied on an approved form at least 28 days before the date from which the licence is to run, or such shorter period as HSE allows. Licences run for up to three years and may carry conditions. Licensable work is broadly the higher-risk categories, notably asbestos insulation, asbestos coating and most work on asbestos insulating board, whereas lower-risk work such as removing asbestos cement sheets can be non-licensed or notifiable non-licensed work. A homeowner should ask which category the material falls into and, if licensable, verify the contractor's HSE licence before any work starts.
- very strong RN-IKZ849
The National Archives (legislation.gov.uk)
Regulation 4 of the Control of Noise at Work Regulations 2005 sets the decibel thresholds that trigger a contractor's duties on a noisy site. Lower exposure action values: a daily or weekly personal noise exposure of 80 dB A-weighted and a peak sound pressure of 135 dB C-weighted, at which hearing protection must be made available and information and training given. Upper exposure action values: 85 dB A-weighted daily or weekly exposure and 137 dB C-weighted peak, at which noise must be reduced by engineering and organisational means, hearing protection zones designated and protection worn. Exposure limit values: 87 dB A-weighted and 140 dB C-weighted peak, which must not be exceeded. Paragraph (5) is the important qualification: the protection given by personal hearing protectors is taken into account when applying the exposure limit values but not when deciding whether the action values have been reached. These are the worker-protection figures, distinct from the statutory nuisance route a neighbour would use.
- very strong RN-NLM9VJ
The National Archives (legislation.gov.uk)
Regulation 4 of the Control of Vibration at Work Regulations 2005 fixes the numbers that govern how long a trade may run a breaker, floor saw, SDS drill or plate compactor, and is the reason a competent contractor rotates operators rather than putting one worker on a breaker all day. Paragraph (1), hand-arm vibration: the daily exposure limit value is 5 m/s2 A(8) and the daily exposure action value is 2.5 m/s2 A(8). Paragraph (2), whole-body vibration: the daily exposure limit value is 1.15 m/s2 A(8) and the daily exposure action value is 0.5 m/s2 A(8). Daily exposure is calculated in accordance with Schedule 1 Part I for hand-arm and Schedule 2 Part I for whole-body vibration. Exceeding an action value triggers a programme of control measures and health surveillance; exceeding a limit value is prohibited. Relevant to any renovation involving extended breaking out of concrete or removal of screed.
- very strong RN-YLNAFQ
The National Archives (legislation.gov.uk)
Regulation 16 of the Electricity at Work Regulations 1989 is the statutory competence test for electrical work, and it applies far more widely than Part P because it is health and safety law rather than building control. The text: no person shall be engaged in any work activity where technical knowledge or experience is necessary to prevent danger or, where appropriate, injury, unless he possesses such knowledge or experience, or is under such degree of supervision as may be appropriate having regard to the nature of the work. There is no register, qualification or scheme named in the regulation; competence is judged against the work being done. For a homeowner the practical use is that a general builder or handyman carrying out electrical work they are not competent to do is in breach of this regulation even where the work is non-notifiable under the Building Regulations and no certificate was ever required.
- very strong RN-FM29A5
The National Archives (legislation.gov.uk)
Regulation 3 of SI 1998/2573 fixes the statutory floor for employers' liability cover. Paragraph (1) provides that the amount for which an employer is required by the Employers' Liability (Compulsory Insurance) Act 1969 to insure shall be, or shall in aggregate be, not less than £5 million in respect of (a) a claim relating to any one or more employees arising out of any one occurrence, and (b) any costs and expenses incurred in relation to any such claim. The £5 million therefore includes legal costs rather than sitting on top of them. This is the number to quote when a homeowner is handed a contractor's insurance schedule and wants to know whether the employers' liability line is at or above the legal minimum; anything below £5 million on a firm with employees is not compliant.
- very strong RN-VRLRZW
The National Archives (legislation.gov.uk)
Regulation 26 of the Gas Safety (Installation and Use) Regulations 1998 sets the checks a gas engineer must carry out and is the basis for the paperwork left behind after a boiler installation or service. Paragraph (1): no person shall install a gas appliance unless it can be used without constituting a danger to any person. Further paragraphs require flued appliances to be connected by permanently fixed rigid pipes and a second-hand appliance to be verified as safe before installation. Paragraph (9) requires that immediately after work on a gas appliance the person examines the effectiveness of any flue, the supply of combustion air, the operating pressure or heat input or where appropriate the combustion performance, and its operation so as to ensure safe functioning, and forthwith takes all reasonably practicable steps to notify any defect to the responsible person, the owner of the premises or the gas supplier. Amended in 2018 to clarify when combustion performance must be assessed.
- very strong RN-QQWKD8
The National Archives (legislation.gov.uk)
Regulation 6 of the Work at Height Regulations 2005 sets the hierarchy every roofer, window fitter and rendering contractor must follow, and it is the answer to 'do they really need a scaffold'. Paragraph (1) requires the duty holder to take account of the risk assessment when identifying measures. Paragraph (2): work must not be carried out at height where it is reasonably practicable to carry out the work safely otherwise than at height. Paragraph (3): where work at height cannot be avoided, suitable and sufficient measures must be taken to prevent, so far as reasonably practicable, any person falling a distance liable to cause personal injury. Paragraph (4): those measures must so far as reasonably practicable use an existing safe place of work and means of access, or otherwise provide sufficient work equipment to prevent a fall. Paragraph (5): where a risk of a fall remains, equipment must be provided to minimise the distance and consequences of a fall, together with additional training, instruction or other measures. There is no minimum height below which the Regulations stop applying.
- very strong RN-HVZ7RL
The National Archives (legislation.gov.uk), Acts of the Scottish Parliament
SCOTLAND. The primary Act behind Scotland's building standards system, in force as amended to 7 September 2026 with section 36(3) still to be inserted by 2026 asp 14 section 7. Section 4 gives the Technical Handbooks their status as guidance documents and section 5 governs compliance with them. Section 7 creates verifiers and certifiers, sections 8 to 16 the building warrant regime including certification of design at section 11 and late applications at section 15, and sections 17 to 21 the completion certificate regime, with section 19 covering certification of construction and section 21 making it an offence to occupy or use a building without a completion certificate. There is no England-style building notice or full plans choice in Scotland: a warrant is applied for before work starts.
- very strong RN-UQJZBJ
Welsh Government (gov.wales)
WALES. Published 3 April 2017 and not updated since, a 3 MB PDF to be read with the September 2013 amendment slip. This is the Welsh Part P, and it is not the same document as England's 2013 edition. Wales did not follow England in narrowing the definition of a special location, so the scope of notifiable domestic electrical work is wider in Wales. Cite this rather than the England Approved Document P for any Welsh rewire, kitchen or bathroom job.
- very strong RN-MQY230
Welsh Government (gov.wales)
WALES, and this is a hard contradiction with England. The Welsh Approved Document P states that notifiable jobs include new circuits back to the consumer unit AND extensions to circuits in KITCHENS and special locations such as bathrooms, and that consumer unit replacements are notifiable. England's Approved Document P 2013 edition defines a special location at regulation 12(9) as only the zone around a bath tap or shower head, extending 2.25 metres vertically and 0.6 metres horizontally from a bath tub or shower tray, or 1.2 metres from a shower head where there is none, plus a room containing a swimming pool or sauna heater, so a kitchen is NOT a special location in England and extending a kitchen circuit there is not notifiable. In Wales it is. The Welsh document also confirms replacement, repair and maintenance work is generally not notifiable even in a kitchen or special location, that in large bathrooms the special location is bounded by the walls of the bathroom, and that conservatories, attached garages, detached garages and sheds are not special locations, so work there is notifiable only if it involves a new circuit.
- very strong RN-4FI6DR
Welsh Government (gov.wales)
WALES. Published 18 June 2026. New building regulations come into force in Wales on 1 JULY 2026, a different commencement from England's building control reforms, made by the Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025 and the Building etc. (Amendment) (No. 2) (Wales) Regulations 2025. The first introduces a requirement for approval before higher-risk building work can begin, known as Gateway 2, a building control approval application process, change control and mandatory reporting of safety issues during the work, a completion approval process known as Gateway 3, the golden thread of information, appeal procedures and transitional arrangements. The second sets roles, responsibilities and requirements for dutyholders involved in any controlled building work, so it reaches ordinary domestic projects and not only higher-risk buildings.
- strong RN-L6FHQQ
Architects Registration Board
ARB's public search of the Architects Register, which ARB describes as the definitive list of all UK architects: if someone is not on the Register they are not an architect. The Register can be searched by an architect's name or by location. ARB is the statutory regulator that also publishes the Architects Code: Standards of Conduct and Practice, sets the annual retention fee, requires professional indemnity insurance, runs the CPD scheme, prosecutes misuse of the title and publishes a table of prosecutions, and handles public complaints through its Professional Conduct Committee. This is the check to run before paying anyone advertising as an architect.
- strong RN-GKVUWW
Architects Registration Board (ARB)
ARB's guidance on the insurance duty that determines whether a homeowner has anyone to claim against if a design goes wrong. Standards 8.1 and 8.3 place the responsibility for holding adequate and appropriate professional indemnity insurance on the individual architect, whether working independently as a sole trader or employed by a practice; an employed architect who is unsure whether the practice's policy covers them must establish that directly, because the responsibility ultimately sits with the individual. Retired architects, and those voluntarily closing a business or entering insolvency, must hold run-off cover for a minimum of six years after ceasing practice, run-off being the form of PII that responds to past liabilities after trading stops. ARB notes that Professional Conduct Committee cases under Standard 8 have covered failure to hold adequate cover, failure to provide evidence of insurance to ARB, dishonestly declaring cover and failing to maintain it, with sanctions up to erasure from the Register.