When building work has been carried out without the required building regulations approval, or when the completion certificate has gone missing, indemnity insurance is often proposed as the quickest way to resolve the issue before a property sale can proceed. It is widely used in UK residential conveyancing, but it is also widely misunderstood.
Indemnity insurance does not make non-compliant work compliant. It does not fix defects, and it does not guarantee that a building will perform safely. What it does do is transfer a specific financial risk, the risk of enforcement action by the local authority, away from the buyer and their mortgage lender. Understanding the difference matters enormously when deciding whether indemnity insurance is the right solution for your situation.
What building regs indemnity insurance covers
A building regulations indemnity policy protects:
- The buyer (and their successors in title, meaning future owners)1
- The buyer’s mortgage lender1
- Against the financial loss arising from a local authority issuing an enforcement notice under Section 36 of the Building Act 1984
Section 36 allows a council to require works to be altered or removed if they contravene building regulations, but only within 10 years of the work being completed (the limit was 12 months until the Building Safety Act 2022 extended it, from 1 October 2023 in England and 1 July 2026 in Wales). After 10 years, the local authority’s power to serve a Section 36 notice lapses.2
The policy also typically covers loss of value to the property if the issue comes to light and affects saleability, and legal costs involved in defending or responding to enforcement action.
What it does not cover
Indemnity insurance does not cover:
- Structural defects or safety issues arising from the work
- The cost of remediation if work is found to be substandard
- Any work that is actively being investigated by the local authority at the time of purchase
- Situations where the buyer has already approached the council about the missing paperwork
This last point is critical. Contacting the local authority is likely to invalidate cover.3 Most insurers will not issue a policy if there has been any contact with the council, because the act of enquiring draws attention to the issue and potentially triggers formal action. If you are considering indemnity insurance, instruct your solicitor before making any calls to building control.
When is indemnity insurance appropriate?
| Situation | Recommended route | Why |
|---|---|---|
| Work completed more than 10 years ago, no council contact | Indemnity insurance | Enforcement window has likely lapsed; risk is low |
| Work completed less than 10 years ago | Regularisation certificate | Enforcement remains live; insurer may refuse |
| Work completed before November 1985 | Indemnity insurance | Regularisation unavailable; only option |
| Structural concerns about the work | Building survey, then regularisation if possible | Insurance covers legal risk, not physical risk |
| Transaction time-critical | Indemnity insurance | Standard policies can often be quoted within minutes |
| Buyer’s lender requires formal sign-off | Check lender requirements first | Some lenders won’t accept indemnity for certain works |
The 10-year enforcement window is the most important factor. Once 10 years have passed since the work was completed (not since the lack of approval was discovered), the council’s power to serve a Section 36 notice has expired.2 This dramatically reduces the underlying risk, and most insurers are comfortable issuing policies in these circumstances.
The window is not absolute. Section 36 does not affect the right of the council, or anyone else, to apply to the court for an injunction to have work removed or altered because it breaks the regulations, and it sets no time limit on that route.2 That is one reason a policy is still worth having on old work.
What building regulations indemnity insurance costs
Premiums are almost always a single one-off payment, not an annual fee. The policy runs with the property and passes to future owners.
| Property value / scenario | Typical one-off premium |
|---|---|
| Up to £250,000, minor works (e.g. no completion certificate for kitchen) | £20–£150 |
| £250,000–£500,000, single extension or loft conversion | £100–£300 |
| £500,000–£1,000,000, larger or multiple items | £175–£500 |
| Complex or high-value properties | Several hundred pounds or more, priced individually |
The HomeOwners Alliance puts a typical building regulations indemnity policy at £20–£300.3 For a house selling for £500,000, it gives around £175 as the usual cost of a very straightforward policy.3 Cover for building work that lacks the right certificates can cost several hundred pounds.1 The bands above are rough guides: the insurer prices each case on the property value and the works.
Who pays? Traditionally the seller pays, since the missing paperwork is their responsibility. However, who pays is open to negotiation: in a buyer’s market the seller usually pays; in a competitive market buyers sometimes absorb the cost to keep the deal moving.3
The regularisation alternative
For work done after 11 November 1985, you can apply to your local authority building control (LABC) for a regularisation certificate, a retrospective approval.4 The council will inspect the work (which may require opening up walls or lifting floors), assess compliance and, if satisfied, issue a regularisation certificate which, like a completion certificate, is evidence (but not conclusive evidence) that the work complies.4
Regularisation fees vary by council and include a surcharge on the normal fee: Hillingdon, for example, charges £440 to regularise a chimney breast removal and £1,210 for an extension under 40 m², with any contractor costs for opening up on top.5 It can take several weeks, which is often too slow for a sale with an exchange deadline. But if the work has any structural or safety dimension, an extension that may not have adequate foundations, a loft conversion where the floor joists are unknown, regularisation is far preferable, because a surveyor and the council inspector will actually assess the work rather than simply covering the legal risk.
How to obtain indemnity insurance
Indemnity insurance for missing building regs is not sold on comparison websites, it is arranged through specialist legal indemnity insurers, almost always via your solicitor or a legal indemnity broker.1 Your conveyancer will typically do this as part of the sale process.3 Your solicitor will recommend an insurer based on the specific risk.
The application process is straightforward: the solicitor completes a proposal form describing the works, their date, the property value and the absence of enforcement contact. A quote can sometimes be given within minutes, but a bespoke policy that an underwriter has to review can take several days.1
Questions to ask before accepting indemnity insurance
Is the work structurally sound? If there is any doubt, commission a structural engineer’s report. Indemnity insurance will not pay for remedial works.
What does your mortgage lender require? Most high-street lenders accept indemnity insurance for older works, but some have specific exclusions, particularly for extensions on listed buildings or in conservation areas. Your solicitor can check the lender’s own requirements in Part 2 of the UK Finance Mortgage Lenders’ Handbook before proceeding; the Handbook is voluntary, so a lender that does not use it has to be asked directly.6
How old is the work? If it was completed less than 10 years ago, discuss regularisation with your solicitor. Some insurers won’t cover very recent works at all.
Has the council been contacted? Be completely honest with your solicitor. Even an informal enquiry can invalidate a policy.
Is this a listed building? Listed building consent issues are a separate matter from building regulations and require separate advice. Some indemnity policies exclude listed structures.
Common scenarios resolved by indemnity insurance
Converted garage: A garage was converted to habitable space in 2009 without building regs approval. The current owners want to sell. The works are over 10 years old, no enforcement action has been taken, and the buyers’ solicitor has requisitioned evidence of compliance. An indemnity policy is arranged within two days at a cost of £220, the transaction proceeds.
Missing completion certificate: A kitchen extension was built in 2015 under a full building regs application, but the final inspection was never called for and no completion certificate was issued. The LABC confirms the application was opened and inspections were made at foundation stage and first-fix, but no final. An indemnity policy is issued noting partial compliance; the buyer’s lender accepts it.
Pre-1985 rear extension: A Victorian terrace has a 1970s extension with no building regs paperwork whatsoever. Regularisation is unavailable. A policy is issued at low cost reflecting the age of the works and the expired enforcement period.
In each case the insurance is a practical commercial solution to a legal gap, not confirmation that the work is safe or compliant.
References (6)
Figures in this note were checked against the sources below on 2 October 2026. Superscript numbers in the text point to them. Every source the site cites, by topic.
- 1costfairHomeOwners Alliance.RN-IWH4C2A price, true at 2026-09. HomeOwners Alliance guide to property indemnity insurance. It says a policy for building work without the right certificates can cost several hundred pounds, against a typical £20 to £300 for indemnity policies generally.
- 2technicalvery strongThe National Archives (legislation.gov.uk), legislation.RN-NKK4KZSection 36(1) lets the building control authority, without prejudice to prosecuting for a fine, serve notice on the owner requiring work that contravenes building regulations to be pulled down or removed, or at the owner's election altered so as to comply. Section 36(2) applies the same power where work was executed without an application for building control approval, despite refusal of one, or otherwise than in accordance with the requirements of a granted application. Section 36(3) gives the owner 28 days, or longer if the appropriate court or tribunal allows, before the authority may carry out the work itself and recover the reasonable expenses. Section 36(4) is the key protection: a section 36 notice may not be given after 10 years from the date the work was completed. Sections 36(5) and 36(5A) bar a section 36 notice where a building control approval application for work that is not higher-risk building work was granted and the work was executed in accordance with the approved plans and any requirement imposed.
- 3costfairHomeOwners Alliance.RN-FTR5SQA price, true at 2026-09. HomeOwners Alliance guide for owners whose property lacks a building regulations certificate. It gives the typical cost of a building regulations indemnity policy as £20 to £300.
- 4technicalvery strongThe National Archives, legislation.RN-4MV2ZGRegulation 18 of the Building Regulations 2010, unauthorised building work. Where work was carried out on or after 11 November 1985 without approval, the owner may apply in writing for a regularisation certificate. This is the route out of discovering at sale that an extension or loft conversion was never signed off, and the date in it is why anything older is outside the process.
- 5coststrong locallyLondon Borough of Hillingdon.RN-XNWC03A price, true at 2026-09. Hillingdon's 2026-27 building control fee schedule lists a regularisation charge for each type of domestic work: £1,210 for an extension under 40 m² and £440 for minor works such as chimney breast removal or a simple structural opening.
- 6technicalgoodUK Finance, guidance.RN-7P1NHDUK Finance's Handbook site explains that each handbook has Part 1 general instructions and Part 2 lender-specific instructions, that it is voluntary, and that lenders not listed must be contacted direct.
-
What Is Indemnity Insurance?, HomeOwners Alliance, accessed 30 September 2026. Priced at 2026-09 and left there. hoa.org.uk
-
Building Act 1984, section 36: Removal or alteration of offending work, legislation.gov.uk, accessed 7 September 2026. legislation.gov.uk
-
No Building Regulations Certificate? What Can You Do?, HomeOwners Alliance, accessed 30 September 2026. Priced at 2026-09 and left there. hoa.org.uk
-
The Building Regulations 2010, regulation 18: Unauthorised building work, legislation.gov.uk, accessed 13 September 2026. legislation.gov.uk
-
Building Control Fees 2026-27, London Borough of Hillingdon, accessed 2 October 2026. Priced at 2026-09 and left there. pre.hillingdon.gov.uk
-
UK Finance Mortgage Lenders’ Handbook, UK Finance, accessed 30 September 2026. lendershandbook.ukfinance.org.uk