When a builder, plumber, or any other trader gives you a price for work, that price is either a quote or an estimate, and the difference between the two is far more significant than most homeowners realise. Getting this wrong can leave you legally exposed or facing a bill that is hundreds or even thousands of pounds higher than you expected.

What Is a Quote?

A quote (also called a quotation) is a fixed, binding offer to carry out specific work for a stated price. Once you accept it in writing, the trader is contractually obliged to complete that work for the agreed sum. They cannot charge more unless:

  • You change the scope of work (a “variation”)
  • Unforeseen conditions arise that could not reasonably have been anticipated (for example, discovering rotten joists once floorboards are lifted)
  • The quote explicitly states it will be adjusted for materials price changes beyond a certain threshold

In practice, reputable traders will document any variation before the extra cost is incurred, ideally with a written change order you both sign.

What Is an Estimate?

An estimate is an approximate indication of likely cost. It is not a fixed price. The final bill can, and often does, differ from the estimate, sometimes substantially. The Consumer Rights Act 2015 requires that where a price has been quoted, consumers pay no more than the quoted price. Where only an estimate has been given, the final charge must still be “reasonable” relative to the estimate, but there is no hard ceiling.

The word “estimate” should set off a mental alarm: ask the trader to clarify the basis, what contingencies they have allowed for, and how variations will be handled.

Key Differences at a Glance

FeatureQuoteEstimate
Binding on the trader?Yes, once acceptedNo
Can the price increase?Only via agreed variationsYes, within reason
Best forWell-defined, measurable jobsComplex or exploratory work
Typical documentFormal quotation letter / breakdownEmail or verbal figure
Your protectionHigh, Consumer Rights Act 2015Moderate, final charge must be “reasonable”
When to ask for itNew extension, kitchen, bathroom, roof replacementStrip-out, investigation works, major structural repairs

When You Will Get an Estimate Rather Than a Quote

Trades will usually only offer an estimate when the full scope genuinely cannot be known upfront:

  • Damp investigation and repair: the extent of damage behind plaster cannot be known until the plaster is off.
  • Drainage repairs: CCTV surveys may reveal more problems than expected.
  • Rewiring older properties: the condition of existing wiring and the number of remediation points cannot always be seen.
  • Underpinning: the depth and extent of foundation failure is uncertain until excavation begins.

In these cases, ask the trader to break the estimate into a fixed-price phase (the investigation) and a second quotation once the full scope is clear. This is standard practice on well-run jobs.

How to Get a Proper Quote

  1. Define the scope precisely before approaching traders. Vague briefs produce vague prices. Provide drawings, specifications, or at minimum a detailed written brief.
  2. Request quotes from at least three traders. This gives you a market benchmark and uncovers wildly high or low outliers.
  3. Ask explicitly: is this a quote or an estimate? If they say quote, ask whether it is fixed or subject to any caveats.
  4. Insist on a written breakdown. A single lump sum offers no protection if a dispute arises. A good quote will separate labour, materials, plant hire, and any allowances or provisional sums.
  5. Understand provisional sums. A provisional sum is a budget allowance for an item whose cost cannot yet be fixed (for example, floor tiles chosen by the client). These are expected to change and are not binding.
  6. Do not read a prime cost sum as the price of the item. A PC sum is a supply-only allowance and nothing more. RICS defines it as excluding “all costs associated with fixing or installation, all ancillary and sundry materials and goods required for the fixing or installation”, the subcontractor’s design, preliminaries, overheads and profit, and the main contractor’s design, preliminaries, overheads and profit on top of that.1 Run a £5,000 PC sum for kitchen units through the main contractor’s share alone, at typical conventions of 11% preliminaries and 2.5% overheads and profit, and it reaches the account at about £5,689, which is 13.8% more before a single hour of fitting. Taking the PC sums out of a quotation and calling them the cost of the kitchen understates it every time. Our note on why a published building rate is not what you pay walks the same additions in full.
  7. Agree how variations will be managed. A contract should state that no extra work is to be instructed without a written variation order signed by both parties before the work begins.

Typical Cost Ranges for Common UK Renovation Jobs (2026)

JobTypical Quote Range
Kitchen supply and fit (mid-range)£8,000 – £20,000
Bathroom refurbishment£4,000 – £12,000
Single-storey rear extension (per m²)£2,200 – £3,500/m²
Loft conversion (dormer, London)£55,000 – £90,000
Full rewire (3-bed semi)£4,500 – £8,000
New boiler supply and installation£2,200 – £4,500

These are illustrative ranges. Your actual quote will depend on specification, location, and site conditions.

Red Flags to Watch For

  • A trader who gives you a quote verbally only and refuses to put it in writing.
  • A quote with no breakdown, just a total figure.
  • Prices that are dramatically below the market range (often a sign the trader will seek to recover margin through variations).
  • No mention of how variations will be priced or approved.
  • Pressure to sign quickly or start before you have read the documents carefully.

What the Law Says

Under the Consumer Rights Act 2015, services must be performed with reasonable care and skill and at a reasonable price if no price was agreed in advance. The Act also gives consumers the right to require repeat performance of substandard work. If a fixed quote was agreed and the trader charges more without your agreement, you are entitled to pay the quoted price only.

For B2B contracts, where you are buying as a business rather than a consumer, the Consumer Rights Act does not apply and the implied terms come from the Supply of Goods and Services Act 1982 for the work and the Sale of Goods Act 1979 for any goods, alongside ordinary contract law. The fundamental principle, that a quote is an offer capable of acceptance, holds either way.

Getting the Best Outcome

The simplest protection is to treat every price you receive with equal suspicion until you understand whether it is fixed or approximate. Ask the question directly. Put everything in writing. And before work begins, make sure you have a signed document, however brief, that states the price, the scope, and what happens if the scope changes.

A trustworthy trader will have no problem providing this. One who pushes back or gets vague is telling you something important.

References (1)

Figures in this note were checked against the sources below on 14 September 2026. Superscript numbers in the text point to them. Every source the site cites, by topic.

  1. 1technicalstrongRoyal Institution of Chartered Surveyors, a standard.RN-K45EY4The rulebook behind every professional cost per square metre figure, and free to download as a PDF from RICS, which makes it directly citable rather than paraphrased. NRM 1 is issued by the RICS Quantity Surveying and Construction Professional Group as one of a suite of three (NRM 1 order of cost estimating and cost planning, NRM 2 detailed measurement for building works, NRM 3 order of cost estimating and elemental cost planning for building maintenance works), all reissued in October 2022 as practice information having been published in October 2021 as guidance notes, with no material change to content. NRM 1 covers quantification of building works for cost estimates and cost plans, and also how to quantify the items that are not measurable building work: preliminaries, overheads and profit, project team and design team fees, risk allowances, inflation, and other development and project costs. It sets out the floor area method for order of cost estimates and defines the terms a note should use precisely: cost per m2 of gross internal floor area (cost/m2 of GIFA) is the unit rate which, when multiplied by the gross internal floor area, gives the total building works estimate, and gross internal floor area (GIFA, also gross internal area or GIA) is defined in Appendix A with reference to the latest edition of the RICS Code of Measuring Practice. It also distinguishes GEA (gross external area) and NIA (net internal area). This is the source to cite for why a cost per m2 figure is meaningless without stating which area basis it uses.
  1. RICS NRM 1: Order of cost estimating and cost planning for capital building works, 2nd edition, Royal Institution of Chartered Surveyors, accessed 11 September 2026. rics.org