Every price on this site is built the same way, from the same set of books, and every one of them is a ballpark. This note explains how the figures are made, where they are checked, and what the confidence level attached to each one means for how far you should trust it.

The short version: we price materials from merchants’ own list prices, labour from published labour times and trade day rates, and installed work by adding the two, then check the result against prices published by other people, including the official rating cost guides. None of that turns a figure into a quote. In the terms of how cost estimates work, every figure here sits at the first level: a cost-guide ballpark.

Five Books, One Source for Every Figure

Every cost figure on the site traces to one of five books:

BookWhat it holdsHow it is made
MaterialsMerchant list prices, ex VAT, and plant and tool hireTaken from the merchant’s own product page, with the quoted price checked
ProductivityThe hours a gang takes per unit of each operationFrom published labour constants, schedules of rates and manufacturers’ fitting times
Day ratesWhat a builder pays each trade per day, plus overheads, profit and non-productive timeWorked out from pay statistics, agreed rates and published labour-only and charge-out rates
FitThe labour-only price per unit of each operationComputed: hours times the gang’s day rate, plus non-productive time, overheads and profit
Supply and fitThe installed price per unitComputed from a recipe: materials with waste, plus labour and plant, plus overheads and profit

The UK Renovation Cost Index gathers the headline ranges from these books in one place, with the basis of each.

The Method We Follow

The books follow the procedure of a published construction estimating manual used by the US Navy, Army and Marine Corps, approved for public release. It breaks a job into work elements, each usually one trade doing one task, and makes a separate estimate of the materials, the plant and the labour for each element.1

Materials are measured as a net quantity, and an allowance for waste is added for each type of material to give the quantity bought.1 Labour is always worked out on the net quantity, never on the waste.1

Every price assumes normal conditions. Known conditions, such as poor access, a home that is lived in during the work, an old building that is out of true or a premium finish, scale the labour task by task, never as one figure on the whole job.1 The estimate builder lets you set these conditions line by line.

Each whole-job price is also checked against a list of general items, such as waste removal, scaffolding, protection, consents and making good, so it is clear what the price includes and what it leaves out.1

The manual’s labour figures are for military crews, and the manual itself puts civilian work at 1.33 to 2 times their pace.1 We use them only as a cross-check where they agree with UK figures, never to lower a UK figure on their own.

Materials

Materials are priced at the merchant’s list price: the price on the merchant’s own product page for the actual product, never a category listing or a search result. The books hold that price ex VAT, because trade counters and merchant accounts work ex VAT and it keeps every figure on one basis. VAT at the standard rate of 20% is then added where the homeowner pays it.2 The notes usually show the VAT-inclusive figure where that is what you would pay, and our note on reading a builders’ merchant quote explains why the same item can carry two prices 20% apart.

A list price is not the best price. Builders with accounts, and anyone buying a full load, usually pay less; anyone buying a single bag usually pays more. We use the list price because it is published and anyone can check it, which a negotiated price is not.

Labour

Labour has two parts: how long the work takes, and what an hour costs.

Time comes from published labour times, the hours a gang takes to lay a square metre or fit an item, taken from labour constants, schedules of rates and manufacturers’ fitting instructions. Day rates start from pay statistics, chiefly the Office for National Statistics’ Annual Survey of Hours and Earnings, which reports earnings and hours by occupation.3 They are cross-checked against agreed industry rates and against labour-only and charge-out rates that firms publish. Our note on what an hour of labour actually costs shows why the wage is only the start of it.

On top of the wage go the costs of running a business: time that is not spent on the tools, overheads, and profit. Overheads and profit are added once, so materials are not marked up twice when they go into an installed price.

Small jobs carry extra overhead

A one-hour job costs a builder much the same in travel, parking, setting up, the van and the office as a full day does. So a per-item job that takes less than a day carries an extra overhead, at its fullest up to half a day and tapering to nothing at a full day. Prices per metre or per square metre are never loaded this way, and an item priced inside a larger job does not carry its own loading. Our note on the costs that only small jobs carry explains the wider problem.

Installed Prices, and How We Check Them

An installed (supply and fit) price is built from its parts: the materials with an allowance for waste, the labour, any plant, and overheads and profit. Each is then checked against prices observed elsewhere: firms’ published installed prices, cost guides and the official rating cost guides. Where the built-up price and the observed prices disagree, the figure is graded down until the disagreement is explained.

The official guides are the Valuation Office Agency’s and the Scottish Assessors’. The Valuation Office Agency’s Rating Cost Guide 2026 prices building work for business rates valuations, built up from actual build costs and industry price books.4 The Scottish Assessors Association publishes a parallel Rating Cost Guide Scotland 2026.5 They are official, published schedules of building costs, and they come with limits that we respect.

  • They are set at a fixed date. The VOA guide’s costs are set at 1 April 2024, the valuation date for the 2026 revaluation.4 A figure checked against them has to allow for price movement since, which our note on bringing an old building price to today’s money explains.
  • They are struck for large contracts. The VOA’s costs are adjusted to the price level of a £4 million contract at a national average location.4 A domestic job is far smaller and costs more per unit, for the reasons in why a published building rate is not what you pay.
  • They are not written for this. The VOA says the guide is for rating valuations only and must not be used for any other purpose.4 We use the rating guides only as an independent check on the level and shape of an installed price, never as the price of your job.

Grants Are Shown Beside the Price, Never Taken Off It

Prices for grant-eligible work, such as heat pumps and biomass boilers, are always shown before the grant, with the grant in brackets beside them. Not every home qualifies, grant amounts change, and a price after grant hides what the installer is actually charging.

The Boiler Upgrade Scheme currently gives £7,500 towards an air source or a ground source heat pump.6 Until March 2027 there is an extra £1,500 for homes heated by oil or LPG with no mains gas connection.6 The grant is taken off what you pay the installer and shown on the quotation and invoice.7 RICS NRM 1 takes the same line for professional estimates, recommending that grants are left out of an order of cost estimate.8 Our guide to the Boiler Upgrade Scheme covers eligibility.

Five Confidence Levels

Every figure in the books carries one of five confidence levels. The level describes the source and how well it has been checked, not how close the figure will be to your quote.

LevelNameWhat it meansHow far to trust it
1OfficialTaken from an official, statutory or published-schedule source (government, councils, the VOA and Scottish Assessors guides), with the quote checkedThe source is as good as it gets. The figure is still a ballpark for your house, and an official schedule may be dated or struck for a different scale of work
2PublishedA merchant’s list price, or a maker’s or firm’s own published price, with the quote checkedA real price someone is charging. Good for materials and simple items; what you pay may differ by account, quantity and region
3CorroboratedComputed from checked inputs, or in agreement with independent observed pricesA reasoned figure that has passed a cross-check. The best level a built-up installed price can reach
4IndicativeA single cost-guide figure, or computed from partly estimated inputsOne source, or some inputs not yet checked. Use as an order of magnitude
5EstimateNo checkable source yetOur own working figure. Treat as a placeholder until it is replaced

A few rules sit behind the levels. A price more than two years old drops a level. Labour-only and installed prices are computed, so they are level 3 at best, and an installed price takes the weighted level of the lines in it. Day rates are worked out from pay statistics and published rates, so they are level 2 at best.

How the Levels Relate to Estimate Accuracy

Confidence and accuracy are different questions. Confidence asks whether a figure is a true statement of what its sources say. Accuracy asks how close it will be to what you end up paying, and that depends on how well your own job is defined.

A level 1 figure from an official guide is a faithful copy of an official number, and it is still a ballpark for your house, because nobody has measured your house. The published accuracy ranges for that level of estimate, set out in how cost estimates work, apply to every figure here, whatever its confidence level. A higher level narrows the risk that the figure is simply wrong; it does not narrow the risk that your job is different.

So use the site’s figures to test whether a project is affordable, to set a first budget with a contingency, and to ask sharper questions of a quote. When a builder’s price is far from ours, the likeliest explanation is a difference in scope, specification, access or region, and it is worth finding out which before deciding who is right.

References (8)

Figures in this note were checked against the sources below on 8 October 2026. Superscript numbers in the text point to them. Every source the site cites, by topic.

  1. 1technicalfairUS Navy, US Army and US Marine Corps, guidance.RN-MFZ9ZJThe joint US Navy, Army and Marine Corps manual on construction estimating: levels of estimate, materials takeoff and waste, equipment and labour estimates, and estimating data by MasterFormat division. Approved for public release.
  2. 2technicalvery strongHM Revenue & Customs (GOV.UK), guidance.RN-4W7T33Sets the three UK VAT rates: standard 20% on most goods and services, reduced 5% on some goods and services such as children's car seats and home energy, and zero 0% on zero-rated goods such as most food and children's clothes. The standard rate rose to 20% on 4 January 2011 from 17.5%. Some supplies are exempt rather than rated, including postage stamps and financial and property transactions. This is the reference for converting a merchant's ex-VAT trade quote into the figure a homeowner actually pays.
  3. 3technicalvery strongOffice for National Statistics.RN-MMT1DOThe ASHE Table 14 dataset gives annual estimates of paid hours worked and earnings for UK employees by sex and by full-time or part-time status, broken down to four-digit Standard Occupational Classification, which is the level that isolates individual construction trades such as bricklayers, carpenters, plasterers and electricians. Released 23 October 2025 as the 2025 provisional edition (zip, about 10.7 MB), with revised and provisional editions back to 2017. A correction dated 19 December 2025 suppressed annual pay estimates for SOC 3312 police officers in some areas; construction occupations are unaffected.
  4. 4technicalvery strongValuation Office Agency, guidance.RN-L37ZLPGuidance Note edition 9 to the Valuation Office Agency's Rating Cost Guide 2026. Explains the methodology behind the estimated replacement costs in the guide and, critically, the adjustments applied to them: the location factor, the contract size adjustment and how the unit rates are meant to be used. Read this before quoting any figure out of the cost guide itself, because a raw ERC without its adjustments is the wrong number.
  5. 5technicalstrong locallyScottish Assessors Association, a government page.RN-IPUQKBThe Rating Cost Guide Scotland 2026: estimated replacement costs per square metre by building type, used by Scottish assessors for contractor's basis valuations. The Scottish equivalent of the VOA guide, and useful as an independent official cost series for the same building types. A replacement cost for rating, not a market tender price.
  6. 6technicalvery strongGOV.UK.RN-9EFNVZThe grant values: £7,500 towards an air source heat pump, £7,500 towards a ground source heat pump including water source heat pumps and those on shared ground loops, and £5,000 towards a biomass boiler. A further £1,500 is available until March 2027 where the property is heated by oil or LPG and has no mains gas connection. Only one grant is available per property. Capacity limits are 45kWth for an individual system, 70kWth for multiple heat pumps and 300kWth for shared ground loops. Hybrid systems pairing a gas boiler with a heat pump are not eligible, and an existing low carbon heating system cannot be replaced under the scheme.
  7. 7technicalvery strongGOV.UK (Department for Energy Security and Net Zero), guidance.RN-11Y5WOThe official GOV.UK page on applying for the Boiler Upgrade Scheme. It settles that the installer applies through Ofgem and the grant is taken off the installation price on the quote and invoice.
  8. 8technicalstrongRoyal Institution of Chartered Surveyors, guidance.RN-Y4KKG3The RICS rules for order of cost estimates and cost plans, 3rd edition (2021, reissued 2022). It states that its estimating and formal cost planning stages are aligned to the RIBA Plan of Work 2020 and the RIBA Digital Plan of Work.
  1. NTRP 4-04.2.3 / TM 3-34.41 / MCRP 3-40D.12, Construction Estimating (October 2021, Change 1 October 2022), US Navy, US Army and US Marine Corps, accessed 9 October 2026. marines.mil

  2. VAT rates, HM Revenue and Customs, accessed 6 October 2026. gov.uk

  3. Earnings and hours worked, occupation by four-digit SOC: ASHE Table 14, Office for National Statistics, accessed 6 October 2026. ons.gov.uk

  4. Rating Cost Guide 2026: Guidance Notes, Valuation Office Agency, accessed 6 October 2026. assets.publishing.service.gov.uk

  5. Rating Cost Guide Scotland 2026, Scottish Assessors Association, accessed 6 October 2026. saa.gov.uk

  6. Apply for the Boiler Upgrade Scheme: what you can get, GOV.UK, accessed 6 October 2026. gov.uk

  7. Apply for the Boiler Upgrade Scheme: how to apply, GOV.UK, accessed 6 October 2026. gov.uk

  8. NRM 1: Order of cost estimating and cost planning for capital building works, 3rd edition, Royal Institution of Chartered Surveyors, accessed 6 October 2026. rics.org